Concrete is the one part of a house you never see again and can never easily put right. What goes into the ground in the first few weeks decides how the building behaves for the rest of its life.
What a foundation is actually doing
A foundation carries a building down to ground that will not move. Carrying the load is the easy half. A two-storey house is light against what most soils can bear. The hard half is stillness: soil swells, shrinks and settles with the seasons, and a building that rides those movements unevenly cracks.
Concrete works carry the same idea outwards. The slab your floor sits on, the base under a garage, the footings under a boundary wall, the structural concrete holding a change in level. Our patch is Gerrards Cross, Beaconsfield and the villages around them. See where we cover. The ground round here refuses to be one thing: chalk, gravel, clay-with-flints and London Clay, all within a few streets.
The families, and who chooses between them
Nearly every domestic foundation is a version of one of four ideas. The ground picks, not the budget, and the choice belongs to your structural engineer.
Strip
A trench with concrete in the bottom and masonry built up off it to damp-proof course. Traditional, and fine where the ground is sound and the dig shallow. Its cost is labour. Somebody lays blocks down a hole that must be held open.
Trench-fill
The same trench, filled with concrete to a few courses below ground level. More concrete, far less bricklaying, nobody working at the bottom. Hence the default on house jobs. On clay near trees, one face usually gets a compressible board, so swelling ground pushes into foam rather than concrete.
Raft
A reinforced slab under the whole footprint, thickened at the edges, carrying the house on all of it at once. For ground that is uniformly poor or gently mobile. Soft spots, made ground, infill plots. An engineered structure with a reinforcement schedule, not a thick slab with mesh thrown in.
Piled
Columns taken down to firm ground, tied at the top by reinforced ground beams. What an engineer reaches for when firm ground is a long way down, or a trench would be too deep to dig safely. Piling is a trade of its own, let separately. We do not pile. On a piled scheme our part starts at the ground beams and the slab above.
What sets the depth
Nobody honest gives a depth over the phone. Approved Document A carries figures for simple strip foundations in England. As a rule of thumb 450mm to clear frost, rising to around 0.75m, 0.9m and 1.0m on low, medium and high shrinkage clay. Treat those as a floor, not an answer. The real number turns on:
- The soil, layer by layer, which is why trial holes come before a concrete price.
- Clay shrinkage: clay swells wet and shrinks dry, lifting and dropping whatever sits in that zone.
- Trees. Species, height, distance. Felled ones too: clay a thirsty tree kept dry swells back for years, and that heave pushes upwards.
- The water table, and whether the sides of a deep trench will stand long enough to pour into.
- Made ground. Old fill, buried foundations, a garden built up over decades. Looks like soil, behaves like rubble.
- Drains and sewers. Building near a public sewer can drive a foundation deeper and may need a build-over agreement, so ask your water company early.
Our guide to foundations goes further, and what happens below your home covers the ground investigation.
Setting out, and the inspection nobody should skip
Setting out is the quietest skill on site and the most expensive to get wrong: lines pulled off the drawing rather than off a fence, diagonals checked so the box is genuinely a rectangle, everything tied to one level datum. Thirty millimetres of error at the first corner is thirty millimetres the bricklayer inherits, and then the roofer. Then the formation, the cleaned-off floor of the dig, is made ready. Spoil out, water out, no soft patches under the pour. Building control looks into the open excavation before any concrete goes in. If the inspection finds roots, soft ground or standing water, the trench goes deeper. That day.
WORTH KNOWING
Building control inspections are notified stages, not favours. In England the rule of thumb is at least one whole day’s notice before a stage is covered up. Anyone offering to pour first and sort the paperwork afterwards is handing you a problem that surfaces when you sell.
Nobody ever admires a foundation. They only ever notice one. And by then it is under a hundred tonnes of house.
Why the mix matters
Concrete is not one material. British practice runs on the designated mixes in BS 8500. GEN for unreinforced work such as trench fill, RC where there is steel in it, PAV where paving must survive frost and de-icing salt, FND where a ground investigation has found sulfates that attack concrete. That last risk is invisible: the wrong mix in aggressive ground looks perfect on the day and softens for years.
Reinforcement earns its keep by being in the right position, not by being present. Bars and mesh sit on spacers so concrete wraps them completely, as a rule of thumb around 75mm of cover where it is cast straight against soil. And concrete gains strength by chemical reaction, not by drying, so every extra litre added at the truck to loosen a stiff load takes strength out of it for good.
WHAT MOVES THE PRICE
- Depth and volume. A metre of trench to two and a half is not a straight line.
- Muck-away: what comes out, and where it is legally allowed to go.
- Groundwater. Pumping, and a trench that will not stand, cost time before money.
- The mix. Reinforced, sulfate-resisting or pumped concrete all price differently.
- Access, root protection areas, heave protection on clay, and winter cover, which is time.
Slabs, oversite and the floor you walk on
Above the foundation sits the oversite, the build-up between ground and finished floor. Hardcore compacted in layers, not tipped in one go and driven over. Clean, inert, free of the sulfates that would attack the concrete above it, and as a rule of thumb no deeper than about 600mm. Then a damp-proof membrane, typically 1200-gauge polythene, joints sealed and lapped into the damp-proof course, continuous rather than nearly continuous. Then insulation, then the slab, which Approved Document C puts at 100mm or more, thicker and reinforced where it is structural. Where fill is deep, a suspended beam-and-block floor is often sounder.
Drainage and service ducts go in while the ground is open. Retro-fitting a pipe through a finished slab costs many times what laying it in the right week does. More in our drainage guide.
Weather decides the last of it. Fresh concrete wants holding above about 5°C until it has hardened, and must never be poured onto frozen ground. In heat and wind the problem reverses: the surface dries faster than the body beneath, and a slab left uncovered crazes. Curing is work, not padding on the programme.
Two things a homeowner can watch for, neither of them technical. Ask to see the delivery tickets. Every load carries one showing the mix and the time it was batched. And notice whether anyone is in a hurry to pour before somebody official has seen the hole. That hurry is the tell.
ASK ANY CONTRACTOR
- Will I see the delivery tickets for every load of concrete that goes in?
- What mix is specified, and has the ground been checked for sulfates?
- How is the extra measured and agreed if the trench has to go deeper, before it is dug or after?
- Who is on site during the pour, and who signs off the finished level?
- Who books the building control inspection of the excavation?
Foundations and concrete are the part of a build with no second chance and no visible reward. Everything after stands on decisions made in a fortnight of mud.
What the ground does here changes street by street. There is more on it village by village.
Planning something on your own plot?